|   | The Lost Creek projects are located on Lost Creek at the
  mouth of Lost Creek
  Canyon in eastern Shasta County, California.
  
 The Lost Creek 1 project consists of a 1.1 MW capacity powerhouse at the end
  of a 2,750 foot long steel penstock. Hydraulic capacity is 65 cfs and the
  gross head is 222 feet. The water is diverted into the penstock at an intake
  structure at the edge of Lost Creek. The intake structure includes a
  self-cleaning fish screen. The turbine-generator is a horizontal shaft
  Francis style turbine with a synchronous generator. Transmission to a third
  party substation is via a 3.4 mile long 12kV transmission line. Operation
  began on December 5, 1989.
 
 The Lost Creek 2 project is located on Lost Creek downstream of the Lost
  Creek 1 project. The project consists of a 450 kW capacity powerhouse at the
  end of a 2,200 foot long steel penstock. Hydraulic capacity is 80 cfs and the
  gross head is 85 feet. A concrete weir diverts project water to the intake
  structure. The intake structure includes a fish screen and automatic screen
  cleaner. The turbine-generator is a horizontal shaft Francis style turbine
  with an induction generator. Transmission to a third party substation is via
  the same 12kV transmission line that Lost Creek 1 uses. Commercial operation
  began on July 29, 1989.
 
 The owner is Snow Mountain Hydro LLC, in which Ida-West Energy Company owns,
  indirectly, a 50 percent interest. Operation and maintenance is performed by
  Ida-West Operating Services, Inc.
 |